start previous pagenext page end   141
FOURTH DECADE  
TESTING AND OTHER APPARATUS
Testing equipment continued to be produced and manufactured in the research laboratories for use in the works and outside. Examples of apparatus developed from 1930 onwards are Schering bridges and discharge bridges for testing condenser bushings and other electrical equipment, turns counters and short-circuit testers for coils, condenser discharge magnetizers for permanent magnets, plating and paint thickness gauges, transmission dynamometers, and finally turbine supervisory equipment for the continuous recording of bearing vibration, shaft eccentricity and differential expansion.

More elaborate was a complete sixteen-element electromagnetic oscillograph made in 1934 for the Switchgear Testing Company. Special apparatus was designed for the electrical recording of instantaneous fluid pressures in oil circuit-breakers under short-circuit conditions when currents of the order of 300,000 A may be encountered, and this involved unusual problems of interference.

In 1931 a high-speed continuously evacuated cathode ray oscillograph with potential divider was designed and constructed by F. P. Burch and R. V. Whelpton, primarily for studies on surge phenomena; it operated with an accelerating voltage of 50 kV and was notably reliable and easy to work, becoming the forerunner of many equipments now in service.

A highly specialized piece of equipment produced for scientific workers in an allied field was a differential analyser, having eight integrating units. Built in 1934 for the laboratory of applied mathematics at Manchester University, this was the first large precision machine of its type in the country. Some years later a similar machine was supplied for the mathematics laboratory at Cambridge.

TECHNICAL

GENERATING plant continued to increase in size and efficiency, and side by side with the Company's technical developments came a greater capacity for carrying out comprehensive installations. An example is a contract completed in 1931 at Montevideo. M-V was the main contractor for the first portion of a power station designed for an ultimate capacity of 120,000 kW, the initial installation comprising two 25,000-kW 3000-r.p.m. turbo-generators and four oil-fired and four coal-fired water tube boilers. The contract was completed in record time, only sixteen months elapsing between the placing of the order and the starting up of the first set; the overall guarantees for the station as a whole, based on the calorific value of the oil or coal used against kilowatt-hours at the outgoing feeders, were completely fulfilled.

STEAM TURBINES
Steam turbine progress was conspicuous both in machines for use under the prevailing operating conditions and in units for operation at 'super pressures'. The